category-icon

Mechanical Anchoring

VIEW RANGE
category-icon

Chemical Anchoring

VIEW RANGE
category-icon

Gas Technology Systems

VIEW RANGE
category-icon

Powder Actuated

VIEW RANGE
category-icon

Power Tools

VIEW RANGE
category-icon

Consumables

VIEW RANGE
category-icon

Construction Chemical Accessories

VIEW RANGE
category-icon

Chemical Anchoring Accessories

VIEW RANGE
category-icon

Tools Accessories

VIEW RANGE
category-icon

Bracing

VIEW RANGE
category-icon

Bolted Connections

VIEW RANGE
Salvation Army Service Centre, Queenstown, NZ
Facing a complex job that involved constructing two buildings and making them into one, Cook Brothers Construction turned to Ramset OrbiPlateā„¢ for the solution.
A complex build, a worthy client, challenging weather conditions ā€“ there were many complexities in the construction of the new Salvation Army Service Centre, just outside of Queenstown.

ā€œEssentially, we had two buildings to construct and then make into one,ā€ explains Site Manager, Stephen Borsboom of Cook Brothers Construction. ā€œOne of the buildings had steel panels that were angled inwards, along with a separate angle on the roof as well. This meant we had a combination of angles to work to, which is why we decided to go with the OrbiPlateā„¢ system.ā€

An additional complexity was that some of the precast panels weighed 25 tonnes, and were just over 12 metres high, making the connections even more challenging. Borsboom said the tolerances provided by the OrbiPlateā„¢ connectors minimised the amount of rework.

The tolerance wasnā€™t allowed for in the design, so Borsboom says the OrbiPlateā„¢ system changed the buildability of the project, preventing the extension of the timeline, as well as being safer, as it eliminated welding at height.

ā€œThe size of these panels in the wind was a contributing factor,ā€ he says. ā€œThe fact that we were able to install the structural steel almost instantly and give us some stability to the building straightaway was significant.ā€

Cook Brothers had never used the OrbiPlateā„¢ connectors before, so it was new to the whole team, even structural engineer Mitchell Bell, with whom they were working.

ā€œI was introduced to them via a colleague, and then put in touch with Ramset before introducing them to the structural engineer,ā€ explains Borsboom. ā€œThis was the first project the engineer had used them for as well.ā€

The projectā€™s structural engineer, Mitchell Bell of Powell Fenwick, said that he received good feedback from the site team after working with the OrbiPlateā„¢ connectors.

ā€œIt made life easier onsite, which makes life easier back in the office as well,ā€ he says. ā€œThis was my first project using them. It was bit different and a change in the way I design but we got good feedback from onsite. We have already worked with them again, after a request from a different builder on another site, so we have used them twice now. They are part of the repertoire now.ā€

ā€œIt increased the construction tolerances a lot,ā€ adds Borsboom. ā€œIt gave us a chance to actually get it right first time. I think on average, we had seven or eight per cent needing reworking instead of the potential for all of them to be redone.ā€

ā€œWe used 360 of them, which would have meant 360 individual welds on a washer if weā€™d gone the traditional route. And washers obviously have four sides. So thatā€™s four times 360, which is a lot of site welding, especially at height. The time cost of that compared to using the OrbiPlateā„¢ā€¦ I donā€™t even know how you could measure that.ā€

ā€œWithout using OrbiPlateā„¢ they would still be drilling steel.ā€

The new 783m2 purpose-built facility is spread over two storeys with Salvation Army operating all their services from the ground floor and associated social services out of the first floor. Itā€™s a much-needed facility for the area and even includes a community theatre.

The Queenstown climate was another consideration during the build, with the team facing challenging weather conditions throughout, which in turns puts pressure on them to do the work as quickly as possible.

ā€œWe work year-round, says Borsboom. ā€œWe continue to work through rain, snow and ice and rain ā€“ itā€™s just another day. Today weā€™ve got torrential sideways rain, and we are expecting 30 to 40 centimeters of snow overnight.ā€

About OrbiPlateā„¢

Ramsetā€™s patented OrbiPlate system delivers orbital connection tolerances of up to 20mm in structural connections. OrbiPlate is quick and easy to install, delivering fine locational accuracy when positioning steel members.

CASE STUDYĀ